Planning, Designing and Project Execution Supervision for Providing Automated Border Control E-Gate Systems at Major Airports of Pakistan

Project Detail

Client:

Pakistan Airports Authority (PAA)

Project Type:

Airport Infrastructure & Border Control Automation

Project Category:

Automated Border Control / E-Gate Systems

Project Overview

This project involves planning, design development, and execution supervision for the implementation of Automated Border Control E-Gate Systems at major airports across Pakistan. The project aims to modernize passenger processing through automated border control technologies, improving operational efficiency, passenger experience, and airport security.

The consultancy services cover complete design development, technical planning, supervision during implementation, and project execution support.

Project Duration

Project Phase Duration
Phase-I Design Services 6 Months
Phase-II Project Execution Supervision 24 Months
Project Execution Supervision 12 Months
Defect Notification Period (DNP) 12 Months
Total Project Duration 30 Months

Project Scope of Services

Key Deliverables

Project Objective

The objective of this project is to introduce modern Automated Border Control E-Gate Systems at major airports in Pakistan to improve passenger processing efficiency, strengthen border security, and support digital transformation within airport operations.

Project Highlights